The Public Works and Engineering Department has many ongoing projects in addition to any emergency repairs or other unforeseen occurrences.

(Updated February 9, 2026)

๐Ÿšง W. Pipeline Road Closure ๐Ÿšง

All lanes from Lee Drive to Forest Ridge will be closed to through traffic on Thursday, February 12, through Saturday, February 14, from 6 a.m. to 7 p.m. Below is the map for the traffic detour.

Flag crews will be in place along the closure to allow residents to exit only in the westbound direction. Residents must re-enter from the same west end.

Morrisdale Estates residents are encouraged to enter and exit Morrisdale Estates via Woodvine Drive to El Camino Real.

We appreciate your patience and cooperation. Please stay safe, watch for signs, and plan your travel accordingly.

Map for Closure

๐Ÿšง Ongoing Projects ๐Ÿšง

  • FY2019 Street Reconstruction of West Pipeline Road:  

    The final phase of construction, rebuilding the northern lanes from Arwine Cemetery to Forest Ridge, is underway. Paving began in early February.

  • FY2023 Wastewater Replacement Project: 

    The project is substantially complete. Walk throughs between City staff and the Contractor have been completed and punch list work is near completion. 

  • 50th Year CDBG Sanitary Sewer Rehabilitation Project: 

    Construction is progressing for the rehabilitation of the sanitary sewer lines in the following locations:

    • Along Fair Oaks Blvd. from Lone Oak Circle to Ash Lane

    • Between 302 โ€“ 413 Shelmar Drive

    • Along Kensinger Court

    Project is near completion. Final clean-up is underway.

Helpful Resources