Baze Road Update

Here are the latest road construction updates for Baze Road:

  • Construction plans are available for viewing by the public in the Office of the City Engineer in the Engineering and Development Building at the City Hall Campus at 201 N. Ector Drive.

  • All right-of-way has been acquired. The franchise utility relocations are complete.

  • The project has been advertised and the bid proposals have been opened and evaluated. The City Council awarded a construction contract for the Baze Road construction at the May 10, 2011 Council Meeting.

  • Water main replacement and storm drain construction are now complete.

  • Concrete pavement on the west side adjacent to Ashbrook Est. should be poured the week of Feb. 6, 2012.

  • Fence, retaining wall and driveway construction is in progress.