Here are the latest road construction updates for Ash Lane:
Construction plans are available for viewing by the public in the Office of the City Engineer in the Engineering and Development Building at the City Hall Campus at 201 N. Ector Drive.
All right-of-way has been acquired. Utility adjustments are complete.
The bid opening was held on July 13.
The Council awarded a construction contract on August 9, 2011.
Storm drain construction is complete. A one-way westbound traffic operation is underway.
Sub-grade excavation and liming operations and paving have begun on the north side.
Paving operations should commence the week of February 13, 2012.
Signal pole relocation should occur the week of February 6, 2012.